A、Proportion of material Concrete
10kg,sand 10kg, architecturl gumwater 0.3kg, water 3kg.miz
them into sand paste according to this
proportion.
|
|
B、Cutting cross-shaped spacer in to "T"
and "L" -shaped,suit for requirement of each
position. |
|
C、Install the
glass blocks with the sand paste layer by layer from top
to bottom, install the spacer between glass blocks to fix
them. |
|
D、After
finished the wall , screw the outer part if spacer off
the glass block. |
|
E、Scrape off
the redundant sand paste, draw the outline of the joint
gap. |
|
F、Rub away the
sand paste and dirt, clean the blocks Finally brush the
waterproof paint in the
jiont. |