Products           Projects             Construction Flow
  Location: Construction Flow
  A、Proportion of material Concrete 10kg,sand 10kg, architecturl gumwater 0.3kg, water 3kg.miz them into sand paste according to this proportion.
  B、Cutting cross-shaped spacer in to "T" and "L" -shaped,suit for requirement of each position.   C、Install the glass blocks with the sand paste layer by layer from top to bottom, install the spacer between glass blocks to fix them.
  D、After finished the wall , screw the outer part if spacer off the glass block.   E、Scrape off the redundant sand paste, draw the outline of the joint gap.   F、Rub away the sand paste and dirt, clean the blocks Finally brush the waterproof paint in the jiont.

©Copyright Chemtrade International.鲁ICP备05006590号
 Tel&Fax : +86-532-86893005 | mailto: chemtrade@trade-chem.com